Use Case
Major Power Utility expedites Community Solar Substation Projects with TDG
Transcend Design Generator (TDG) expedited the process of selecting optimal substation locations for a major power utility’s community solar projects. By running multiple conceptual designs and generating detailed documentation, TDG enabled quick decision-making, leading to faster bid solicitation, reduced risk of scope changes, and streamlined vendor evaluation.
Introduction
Situation
Who
Task
The Substation Physical Design Team reviewed several possible substation locations within each potential site provided by the Development Siting Team.
The Substation Design Discipline Lead worked with Utility Procurement to conduct a “Fast Track” bid with all 4 preferred Engineering consultants. Engineering was looking for opportunities to ensure quality bids from all vendors.
Action
Results
After 15 different substation designs, 5 options for each of the 3 proposed locations, the location most suitable was selected, and the preferred design configuration was provided to the supply chain with all associated engineering documentation. This led to a faster solicitation for Bid as well as mitigated risk associated with bids providing low-fidelity technical requirements.
All 4 engineering firms responded to the RFP within the allowed time, due in large part to the guesswork being taken out of the technical preferences of the bid evaluators. Additional time was saved by needing to do only limited validation of Site layout requirements for each of the 3 community solar sites.
The Bid Evaluation team was pleased to find that all 4 vendor bids were within 20% of each other in the category of cost and schedule. The bid evaluators were able to make apples-to-apples comparisons between vendors as the underlying design solutions were highly similar.
One preferred Engineering consultant identified an opportunity to include additional maintenance considerations in their proposal. Extra time was provided to do this because the physical design engineers who would normally spend time validating substation layout fit, were instead able to spend time on substation layout optimization due to the technical information provided in the RFP.
